Building Materials & Real Estate

Welsh Water lodges plans for Cwm Taf, its biggest-ever infrastructure project

The two-package water treatment programme is being market-tested ahead of procurement opening in early 2027 under Ofwat's Direct Procurement for Customers model.

Maren KjellbergOctober 28, 20265 min read3 views
Concept illustration of a planned water treatment site in a green valley, with sedimentation tanks, a storage reservoir, a pumping station and connecting pipelines.

Welsh Water has lodged plans for the Cwm Taf scheme, which the company describes as the biggest infrastructure project in its history. The programme is intended to replace treatment assets that have served the region for more than a century.

Contractors and investors are already being sounded out ahead of procurement, which is due to start in early 2027 under Ofwat's Direct Procurement for Customers model.

The main construction package centres on a new water treatment works at Dan-y-Castell Farm near Merthyr Tydfil. The same package covers treated water storage, a new pumping station at Pontsticill and the connecting pipelines.

A second project will upgrade Llwyn-onn Water Treatment Works in the Bannau Brycheiniog National Park, adding water storage and pipeline connections at that site.

Across the two projects, the proposed scope spans new treatment works, treated water storage, pumping and pipeline connections.

The scheme remains at planning stage: the plans have been lodged, construction has not started, and a delivery partner has yet to be chosen through the procurement that opens in 2027.

The details published so far set out the scope of works and the procurement route; figures for capital cost, treatment capacity and construction timing are not included.