The North East authority behind a £1bn Tees Valley transport wish-list has begun market engagement with construction firms, asking how the potential work should be packaged for procurement.
The five-year programme, submitted to the Department for Transport, runs from April 2027 to March 2032. It covers major road schemes, railway upgrades, bus infrastructure, active travel and transport technology.
The Government has already confirmed £978m of core transport funding for the region. The wider programme, however, includes projects that still require further business case approvals and additional financial backing. Not all listed schemes are therefore fully funded or cleared to proceed. The £1bn figure describes the wider wish-list rather than a guaranteed funding total, a distinction relevant to procurement planning.
Schemes on the list
The authority’s list includes the Darlington Northern Link Road, upgrades to the A66 and A689 corridors, a new platform at Middlesbrough Station and the redevelopment of Thornaby Station.
It also includes a proposed new station at Teesside International Airport, improvements to Middlesbrough bus station and transport links serving the Teesworks development.
The authority has acknowledged that delivering the full programme will depend on Government support and potentially further outside funding. Steve Harker, the combined authority’s cabinet member for transport and infrastructure, said major transport schemes often require significant additional funding even for a devolved body.
Government backing is vital, he said, because it would allow external bodies to help fund the programme and give the region the best chance of delivering as many projects as possible in good time.
Procurement and supplier feedback
Despite the funding uncertainties, the authority is pressing ahead with early supplier engagement to prepare its procurement strategy. It expects to let multiple contracts covering highways, rail, civil engineering and specialist infrastructure rather than award one giant deal.
It is also considering a programme-wide alliance using the FAC-1 Framework Alliance Contract model. The aim would be to bring together delivery partners and encourage regional contractors and SMEs to participate.
An initial supplier launch event was held on 9 November. Firms are now invited to provide feedback through a market engagement questionnaire, with responses due by 1 March 2027.
The engagement is intended to help the authority shape contract packaging and consider an alliance before procurement begins. The authority is gathering feedback as it prepares its procurement strategy for a pipeline that combines confirmed core funding with schemes still subject to approvals and additional backing.